The anatomy of a progress claim
A typical interim payment certificate shows the gross value of work done to date, less the amount certified previously, giving this period’s gross value. From that, the client deducts retention at the contract rate and a proportion of the advance payment. VAT is then added on the amount the contract says is invoiced.
Your ledger should record the certified amount, not your submitted claim. The difference between claimed and certified is a commercial matter until the consultant agrees it; booking it as revenue inflates profit and receivables.